Project Overview

1800 Weston Road

1800 Weston Rd is a proposed award-winning residential development that supports an upgraded pedestrian public realm and responds to the evolving context of the neighbourhood.

The proposed development is located at 1800 Weston Road, south of Lawrence Avenue, with spectacular views of the Humber River and Valley Lands.

1800 Weston Road is a 40 Storey tower on top of a 6-storey podium that offers a total of 488 units, approximately 4,187 SF of non-residential space and 324,073 SF of residential space.

The Site

The proposed development is located at 1800 Weston Road, south of Lawrence Avenue, with spectacular views of the Humber River and Valley Lands.

1800 Weston Road is a 40 Storey tower on top of a 6-storey podium that offers a total of 488 units, approximately 4,187 SF of non-residential space and 324,073 SF of residential space.

 

We anticipate the following milestones will be reached

 

2022

  • Digital survey circulated to collect community feedback on proposed project objectives

  • Finalize project objectives informed by community input to drive the concept design

  • Preparation of preliminary project concept design

  • Financial feasibility review of the project concept design to confirm viability

  • Finalize preliminary project concept design

  • Community Update Meeting #1 to review the preliminary concept design and gather Weston community and stakeholders feedback and revise plan to respond to feedback

  • Preparation of Official Plan Amendment, Zoning Bylaw Amendment, and Site Plan Approval application submission materials

  • Submit Rezoning, Official Plan Amendment, and Site Plan Approval Application to City (process is approximately 12-18 months)

  • Respond to formal City comments on the Rezoning, Official Plan Amendment, & Site Plan Approval application through formal resubmissions (iterative process)

2023

  • Submit Site Plan Application and Zoning By-Law Amendment

  • Host community in-person/virtual meeting with community and stakeholders at key milestones (likely quarterly)

 

Project Timeline

April 2022

June 2023

Development team kicks off project by selecting core consultant team members. Team commences preliminary concept design.


May 2022

Launch project website and project objectives survey. Collect community feedback and use to inform the preliminary concept design.


June 2022

Community Update Meeting #1 to showcase preliminary concept design. Following the meeting, digital feedback surveys will be circulated for additional feedback.


Design team refines concept informed by community stakeholder’s feedback. This project website will be updated with a post outlining “what we heard” following the meeting and review of the digital feedback surveys.


July - August 2022

Prepare technical materials for application submission.


August 2022 - September 2022

A formal submission for a Rezoning, Official Plan Amendment, and Site Plan Approval application is made to the City of Toronto. The full application will be posted to this project website.


Submit Site Plan Application and Zoning By-Law Amendment to the City.

February 2023


Community Consultation Meeting will be hosted by the City on June 27th.